Project – Design and Construction of the complete Civil & Electrical Infrastructure, Power evacuation arrangements including materials, 41 numbers of 1.6MW each Wind Turbine.


  • Capacity – 65.60MW ( 41 towers of 1.60 MW Each)
  • Location – Karad, Satara Dist. Maharashtra, India.
  • Project Cost – 90.00 Cr.
  • Completed and commissioned in 1st July 2013.



  • Location – Karad, Satara Dist. Maharashtra, India
  • Project Cost – 90.00 Cr.
  • Completed and commissioned in 1st July 2013.
  • 41 numbers of Wind Mill Foundations,
  • 41X1.6MW Turbines,
  • 41numbers of 33KV Substations,
  • 220 KV Main Substation,
  • 11 KV Transmission Lines
  • 17.20 km of Infrastructure works